Off-plan villa in Bali: how to pay and what to check before the deposit
An off-plan villa in Bali is bought before it exists. The thing you pay for first is not a building: it is a land or lease right, an approved design, a permit path and a construction promise, and each of those four has its own evidence. Buyers who treat the walkthrough of a show villa as proof of all four are the ones who discover the gap eighteen months later, when the calendar is empty and the certificate of building function is still somewhere in an office.
This page sets out the order of checks for an off-plan purchase, the payment schedule that matches it, and the contract terms that decide who carries the risk when the schedule slips. For the document side of an existing building, the PBG and SLF due-diligence checklist is the companion read. For the entity that will hold the asset, use the PT PMA ownership guide. If you are still weighing a new build against ready stock, the villa build cost guide keeps the two ledgers apart.
What the first payment actually buys
Start with the ground, not the render. A foreign buyer cannot hold Hak Milik, the freehold title reserved for Indonesian citizens, so the acquisition normally runs through a long lease over land held by an Indonesian owner, with building rights registered against it, or through a company structure that holds the right to build and operate. Either way, the parcel is the foundation of the deal, and an off-plan schedule should identify it precisely: district and village, certificate number, the name of the lessor, the term of the lease and where it starts and ends.
Two failures happen here more often than anywhere else in the file. The first is a lease that is shorter than the term the buyer believes they are buying, because the developer's own lease over the plot ends earlier than the sub-lease being sold to you. The second is a plot whose boundaries in the certificate do not match the ridge of the site, or whose access road crosses land the developer does not control. Both are answerable before a booking fee changes hands, and neither is answerable afterwards at the same price.
A booking fee is the weakest instrument in the schedule and should be the smallest. It holds a unit while documents are produced; it should not be described as a reservation of rights, and it should be refundable if the permit file or the title cannot be produced within the agreed window.
The permit path that has to exist before the slab
In Indonesia the building regime is administered through SIMBG, with Government Regulation No. 16 of 2021 as the central implementing rule for building approval. Persetujuan Bangunan Gedung, the PBG, is the approval for the building work itself: constructing, changing, extending or maintaining a structure to technical standards. Sertifikat Laik Fungsi, the SLF, is a separate certificate: it states that a completed building is fit for its approved function, and Government Regulation No. 28 of 2025 requires a business actor to hold it before the building is used.
For an off-plan purchase the sequencing matters more than the paperwork. Spatial conformity comes first: a plot has to be in an area where the intended use is allowed, and in Bali that question is answered against the provincial spatial plan set by Provincial Regulation No. 2 of 2023 together with regency-level controls, not against the colour of a map in a sales deck. Approved drawings come second, and they are the only reliable description of what will stand on the site. The SLF comes last, at completion, and it is the moment when a villa rented to guests either becomes usable in practice or becomes a legal problem with a pool.
So the file you ask for at signing is not a promise to obtain permits. It is the current PBG or, for an older structure being extended, the legacy IMB and the approval for the later work, the approved architectural, structural and building-services drawings, the spatial confirmation for the parcel and the operating entity's business licensing through OSS with the accommodation classification that matches how the villa will actually be sold. Accommodation is not one activity: a tourist cottage under one classification and a non-starred hotel-level operation under another carry different permitting, different staffing obligations and different tax treatment, and the code on the document decides which one you are building.
A payment schedule built on milestones, not on dates
A calendar-driven schedule protects the seller. A milestone-driven schedule protects both sides, because every payment has an object you can inspect. The shape that works is a small booking fee, a signing payment released against a complete document file, then construction stages tied to verifiable progress: foundations, structure and roof, wet areas and services, finishing, and handover with the SLF in the buyer's entity name.
Two rules keep the schedule honest. First, no substantial payment before the permit and the approved drawings exist, because construction without them is the risk you are paying to avoid. Second, a holdback of a few percent stays with the notary or the buyer until the snag list is closed and the SLF is issued, so the last invoice is answered by a finished building rather than by a promise of one.
Percentages vary by developer and by stage, and the split matters less than the trigger behind each line. What a buyer should refuse is a schedule where the majority of the price is paid before the structure is up, or where the final payment is due on a key handover that is defined as "practical completion" with no certificate behind it.
Stage by stage: what to demand and what to refuse
| Stage | Evidence to require | Red flag |
|---|---|---|
| Booking fee | Written offer naming the parcel, unit, price basis and refund condition | Transfer to a personal account |
| Signing | Land certificate, lease deed, PBG or IMB, approved drawings, spatial confirmation, OSS licence of the operating entity | Drawings promised "after the contract" |
| Foundation | Site report with dated photographs and the supervising engineer's confirmation | Report repeats the contractor's own words |
| Structure and roof | Inspection of dimensions against approved drawings; invoices for materials delivered | Payments ahead of visible progress |
| Services and finish | Specification annex reconciled with what is installed; water, power, wastewater connections | Substitutions without written consent |
| Handover | SLF, snag list closed, as-built drawings, warranty documents, inventory for rental use | Keys handed over before the certificate |
Contract terms that decide who carries the risk
Four clauses do most of the work, and they are worth arguing about before anything is signed. The first is the delivery definition: a fixed date, a defined state of completion, and the SLF listed as a condition of delivery rather than an aspiration afterwards. The second is delay: a penalty that accrues per period of delay and a right to terminate after a defined threshold, because a schedule without a consequence is a forecast.
The third is price movement. A construction contract can legitimately carry an escalation clause for materials; it should not carry an open-ended one that leaves the total unknown at handover. The fourth is the exit: what happens if the permit is refused, if the parcel turns out to be unbuildable, if the buyer's own financing fails, and how a refund is calculated at each stage. An off-plan contract that does not describe the refund mechanism is describing a donation with a construction theme.
Alongside the four, three annexes belong in the file: the specification sheet with materials and equipment named rather than described, the payment schedule with milestone triggers written out, and the drawings stamped as approved. Payment should move through a notary escrow or a documented stage account, not into an operating account with an informal promise attached.
Checking the developer and the site
Visit finished projects and talk to the people who live in them, not only to the sales team. Ask who actually builds: an in-house team, a single main contractor or a rotating set of subcontractors, and whether the structural works are supervised by an engineer with a name on the drawings. Ask for the previous project's handover date against its original schedule. A developer who is honest about one late project is more useful than one with a portfolio of perfect stories.
On the site itself, check the things a render cannot show: soil and slope, access for trucks and concrete, drainage and where rainwater goes in February, the power capacity available from the nearest connection, the water source, and the distance to the neighbours whose sleep the villa will interrupt. If the villa is meant to earn, walk the access road as a guest would, with luggage, at night.
The costs that begin after the handover
An off-plan budget that stops at the construction price is incomplete. Furniture, kitchen equipment, linen, pool and garden setup, photography and listing preparation all land between the handover and the first booking, and none of them appear on a construction invoice. Staffing follows: housekeeping, pool and garden, maintenance and a supervisor layer, with payroll obligations attached. A management layer, whether in-house or an outside operator, typically costs somewhere between 15 and 30 percent of rental revenue depending on scope, with booking-only arrangements lower and full operations higher.
The revenue side needs the same honesty. Bali is a seasonal market: a well-run villa can sit near the low 90s percent of occupancy in July and fall into the 40s in February, so an annual model that assumes an average month every month overstates the first year. The remaining lease term has to be long enough to cover the payback you have modelled, and the payback has to be calculated from the net figure, not the gross one.
When to walk away
Some files do not get better with negotiation. Walk away when there is no PBG and no answer about which approval covers the work already done; when the approved drawings cannot be produced because they were never approved; when the certificate, the lease deed and the plot on the ground describe three different areas; when the seller wants the majority of the price before the structure stands; when payments are directed to a personal account; and when the delivery definition has no certificate behind it. Each of these is a documented gap, and a gap in the file becomes a gap in the asset.
Done in this order, an off-plan purchase is a normal project with named risks and a schedule that can be enforced. The deposit goes last, not first, and it goes against documents that a lawyer and a licensed technical reviewer have read, not against a brochure.